GROUND BREAKING CEREMONY APRIL 23,
2009, 6:00 pm Ride the shuttle bus from the current High School. UPDATE: April 13, 2009 The Board reviewed the drawings for the new High School and approved the updated timeline for High School and
East Elementary
2007 BOND ISSUE HALLSVILLE INDEPENDENT SCHOOL DISTRICT HALLSVILLE,
TEXAS Revised April 13, 2009
PROJECT SCHEDULE - HIGH SCHOOL Milestone
Finalize Curriculum Model Obtain Survey Finalize Land Purchase Finalize Program Complete
Initial Bldg. Org. Schematic Complete Schematic Design (site, building) HISD Board Meeting (Update) Complete
Schematic Design Complete Design Development HISD Board Meeting (Update) Formally Start
Construction Docs HISD Board Meeting (Update) Receive 35% CD Check Set 35% CD Review HISD Board Meeting
(Update) HISD Board Meeting (Update) Receive 85% CD Check Set 85% CD Review HISD Board Meeting (CD Approval) Go to Printer Release Site CD Receive 100% CD Receive Bids (Site) Finalize Bid/Negotiate GMP (Site) 100% Final CD Review Complete Construction Documents HISD Board Meeting (CD Approval) Go to Printer (Building) Release Building Sets to WRL HISD Board Meeting (Approve Site) Start Site Construction HISD Board Meeting
(Update) Receive Bids Finalize Bid HISD Board Meeting (Approve Bids) Finalize Contracts Start Construction Complete Construction North Complete Construction Center1 Complete Construction Center2 Complete Construction
South1 Complete Construction South2 Complete Construction - All Start School Fall Semester
PROJECT SCHEDULE NORTH ELEMENTARY (NEW ELEMENTARY SCHOOL)
|
May 15, 2008 August 1, 2008 August 19, 2008 September 8, 2008 September 22, 2008 March 27, 2009 April 13, 2009 April 20, 2009 May 11, 2009 May 11, 2009 May 12, 2009 June 8,
2009 June 22, 2009 June 25, 2009 July 13, 2009 August 10, 2009 September 7,
2009 September 11, 2009 September 14, 2009 September 15, 2009 September 18, 2009 October 5, 2009 October 6, 2009 October 9, 2009 October 9, 2009 October 12, 2009 October 12, 2009 October 13, 2009 October 16, 2009 October 12, 2009 October 29, 2009 November 9, 2009 November 19, 2009 December
10, 2009 December 14, 2009 December 30, 2009 January 4, 2010 February 4, 2012 March 4, 2012 April
4, 2012 May 4, 2012 June 4, 2012 June 4, 2012 August 21, 2012
|
Duration
3 Weeks 3 Weeks
6 Weeks 3 Days
11 Weeks 4 Days
3 Days
4 Weeks 2 Weeks 3 Days 5 Days
4
Days
5 Weeks 3 Weeks
2 Weeks
25 Months 26 Months 27 Months 28 Months 29 Months 29 Months
|
Status
Completed Completed Completed Completed Completed Completed Completed Pending Pending
|
|
Milestone
Obtain Environmental Site Assessment Finalize Curriculum Model Finalize Program Obtain
Survey Finalize Land Purchase Complete Initial Bldg. Org. Schematic Complete Schematic Design (site, building) HISD Board Meeting (Review) Complete Design Development Receive 35% CD Set 35% CD Review HISD Board
Meeting (CD Approval) Receive 85% CD Set 85% CD Review Receive 100% CD Set 100% Final Review Complete
Construction Documents Go to Printer Release CD to WRL Receive Bids Finalize Bids HISD Board Meeting
(Approve GMP) Contract Finalize (WRL) Start Construction Complete Construction Start School Fall Semester
PROJECT SCHEDULE EAST ELEMENTARY (INTERMEDIATE RENOVATION)
|
Completion Date
April 17, 2008 March 26, 2008 May 6, 2008 August 1, 2008 August
28, 2008 October 1, 2008 December 1, 2008 February 9, 2009 February 9, 2009 May 11, 2009 May
13, 2009 June 9, 2009 June 15, 2009 June 17, 2009 June 29, 2009 July 3, 2009 July 7, 2009 July 8, 2009 July 10, 2009 August 20, 2009 September 3, 2009 September 14, 2009 September 28, 2009 October 1, 2009 February 1, 2011 August 22, 2011
|
2 Days
5 Weeks 2 Days 3 Weeks 4 Days
2 Days
5 Weeks 2 Weeks
2 Weeks
16 Months
|
Status
Completed Completed Completed Completed Completed Completed Completed Completed Completed Pending
|
|
Obtain Existing Plans and Coord. Elec. Files Finalize Curriculum Model Finalize Program Complete Initial Building Org. Schematic Complete Schematic Design (site, building) Complete Site and Bldg. Design
Development Complete Construction Documents Go to Printers Release to CM for Bidding Pre-Bid Conference Receive Bids Start Construction Complete Construction Occupy New Building Addition Upon Comp. Start Renovation Constructions Complete Renovation Construction Start School Fall Semester Start School as
Elementary Mid-Sem (option) Start School as Elementary Fall Sem (option)
|
Completion Date
March 1, 2008 March 26, 2008 May 6, 2008 June 6, 2008 July 1, 2008 August 1, 2008 December 15, 2008 February 1, 2008 March 1, 2009 March 1, 2010 March 8, 2010 March 8, 2010 August 8, 2010 August 25, 2010
|
Duration
4 1/2 Months
1 1/4 Months 3/4 Month 12 Months
5 Months
|
Status
Completed Completed Completed Completed Completed Completed Pending
|
 |

Revised November 13, 2008