GROUND BREAKING CEREMONY
APRIL 23, 2009, 6:00 pm
Ride the shuttle bus from the current High School. 

UPDATE: April 13, 2009  

The Board reviewed the drawings for the new High School and approved the updated timeline for High School and East Elementary

divider1.jpg

2007 BOND ISSUE
HALLSVILLE INDEPENDENT SCHOOL DISTRICT
HALLSVILLE, TEXAS

Revised April 13, 2009

PROJECT SCHEDULE - HIGH SCHOOL
Milestone

Finalize Curriculum Model
Obtain Survey
Finalize Land Purchase
Finalize Program
Complete Initial Bldg. Org. Schematic
Complete Schematic Design (site, building)
HISD Board Meeting (Update)
Complete Schematic Design

Complete Design Development
HISD Board Meeting (Update)
Formally Start Construction Docs
HISD Board Meeting (Update)
Receive 35% CD Check Set
35% CD Review
HISD Board Meeting (Update)
HISD Board Meeting (Update)
Receive 85% CD Check Set
85% CD Review
HISD Board Meeting (CD Approval)
Go to Printer
Release Site CD
Receive 100% CD
Receive Bids (Site)
Finalize Bid/Negotiate GMP (Site)
100% Final CD Review
Complete Construction Documents
HISD Board Meeting (CD Approval)
Go to Printer (Building)
Release Building Sets to WRL
HISD Board Meeting (Approve Site)
Start Site Construction
HISD Board Meeting (Update)
Receive Bids
Finalize Bid
HISD Board Meeting (Approve Bids)
Finalize Contracts
Start Construction
Complete Construction North
Complete Construction Center1
Complete Construction Center2
Complete Construction South1
Complete Construction South2
Complete Construction - All
Start School Fall Semester

PROJECT SCHEDULE
NORTH ELEMENTARY
(NEW ELEMENTARY SCHOOL)


Completion Date

May 15, 2008
August 1, 2008
August 19, 2008
September 8, 2008
September 22, 2008
March 27, 2009
April 13, 2009
April 20, 2009
May 11, 2009
May 11, 2009
May 12, 2009
June 8, 2009
June 22, 2009
June 25, 2009
July 13, 2009
August 10, 2009

September 7, 2009
September 11, 2009
September 14, 2009
September 15, 2009
September 18, 2009
October 5, 2009
October 6, 2009
October 9, 2009
October 9, 2009
October 12, 2009
October 12, 2009
October 13, 2009
October 16, 2009
October 12, 2009
October 29, 2009
November 9, 2009
November 19, 2009
December 10, 2009
December 14, 2009
December 30, 2009
January 4, 2010
February 4, 2012
March 4, 2012
April 4, 2012
May 4, 2012
June 4, 2012
June 4, 2012
August 21, 2012


Duration



 




3 Weeks
3 Weeks



6 Weeks
3 Days


11 Weeks
4 Days

3 Days

4 Weeks
2 Weeks
3 Days
5 Days


4 Days




5 Weeks
3 Weeks

2 Weeks

25 Months
26 Months
27 Months
28 Months
29 Months
29 Months


Status

Completed
Completed
Completed
Completed
Completed
Completed
Completed
Pending
Pending

Milestone

Obtain Environmental Site Assessment
Finalize Curriculum Model
Finalize Program
Obtain Survey
Finalize Land Purchase
Complete Initial Bldg. Org. Schematic
Complete Schematic Design (site, building)
HISD Board Meeting (Review)
Complete Design Development
Receive 35% CD Set
35% CD Review
HISD Board Meeting (CD Approval)
Receive 85% CD Set
85% CD Review
Receive 100% CD Set
100% Final Review
Complete Construction Documents
Go to Printer
Release CD to WRL
Receive Bids
Finalize Bids
HISD Board Meeting (Approve GMP)
Contract Finalize (WRL)
Start Construction
Complete Construction
Start School Fall Semester

PROJECT SCHEDULE 
EAST ELEMENTARY
(INTERMEDIATE RENOVATION)

Completion Date

April 17, 2008
March 26, 2008
May 6, 2008
August 1, 2008
August 28, 2008
October 1, 2008
December 1, 2008
February 9, 2009
February 9, 2009
May 11, 2009
May 13, 2009
June 9, 2009
June 15, 2009
June 17, 2009
June 29, 2009
July 3, 2009
July 7, 2009
July 8, 2009
July 10, 2009
August 20, 2009
September 3, 2009
September 14, 2009
September 28, 2009
October 1, 2009
February 1, 2011
August 22, 2011

Duration











2 Days

5 Weeks
2 Days
3 Weeks
4 Days

2 Days

5 Weeks
2 Weeks

2 Weeks

16 Months

Status

Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Pending

Milestone

Obtain Existing Plans and Coord. Elec. Files
Finalize Curriculum Model
Finalize Program
Complete Initial Building Org. Schematic
Complete Schematic Design (site, building)
Complete Site and Bldg. Design Development
Complete Construction Documents
Go to Printers
Release to CM for Bidding
Pre-Bid Conference

Receive Bids
Start Construction
Complete Construction
Occupy New Building Addition Upon Comp.
Start Renovation Constructions
Complete Renovation Construction
Start School Fall Semester
Start School as Elementary Mid-Sem (option)
Start School as Elementary Fall Sem (option)

Completion Date

March 1, 2008
March 26, 2008
May 6, 2008
June 6, 2008
July 1, 2008
August 1, 2008
December 15, 2008
February 1, 2008
March 1, 2009
March 1, 2010
March 8, 2010
March 8, 2010
August 8, 2010
August 25, 2010

Duration






4 1/2 Months



1 1/4 Months
3/4 Month
12 Months

5 Months

Status

Completed
Completed
Completed
Completed
Completed
Completed
Pending

Print

schedule_download.jpg

Revised November 13, 2008

This link requires Adobe Acrobat Reader.